Mt. Vernon Road
Location
Sandy Springs, GA
Manhours
26,000
Crew Size
26
Project Manager
Jason McConnell
Superintendent
Lane Sanford
HSE Professional
James LeBert
Work Scope
This project consisted of combined amount of 3,000 LF of 6” and 12” steel pipe installed in the street. Location was extremely high traffic flow. SEC crews were restricted to night work only with time constraints 7:00pm to 5:30am. The project execution plan consisted of pre-excavation (slot trenching) of the pipe trench with hydrovac trucks to identify all known and unknown utilities. Our crew completed this surgical pipe installation with zero line strikes. This project was completed in Summer 2020.